How do service charge challenges fare at the Eastern tribunal?

Across 266 First-tier Tribunal service charge decisions heard in the Eastern region (2019–2026), 40.4% of 1,498 challenged items were reduced or disallowed; the median reduction, where made, was 48%. (n=1,498, as of 4 July 2026)

Cases are assigned to a region by the First-tier Tribunal venue code in the case reference. These figures are recomputed nightly from the published decisions.

About these figures: Outcomes reflect disputes that reached the First-tier Tribunal, not portfolio-wide quality. Small samples are noisy; every figure links to the underlying decisions.

Outcomes by cost head in Eastern

Cost headItems (n)Reduced or disallowedMedian reduction when reduced
Gardening & grounds4854.2%51.9%
Other charges36845.1%61.9%
Cleaning8938.2%43.2%
Buildings insurance14928.2%17.7%
Repairs & maintenance23237.1%60.9%
Major works17421.3%61.5%
Lifts3036.7%62%
Management fees13056.9%27.8%
Legal & professional costs6457.8%50%
Reserve fund contributions4835.4%48.1%
Administration charges5076%
Utilities9229.3%28.9%

Methodology

These statistics are computed from the published decisions of the First-tier Tribunal (Property Chamber) in service charge cases (case types LSC, LIS and LDC). Each decision is parsed into a structured record — the sums challenged, the sums allowed, the outcome per cost head, and the orders made — and the aggregates on this page are recomputed nightly in plain arithmetic from those records. No figure on this page is estimated, modelled or hand-typed; each carries its sample size. Current corpus: 2,383 decisions covering 12,898 individually disputed items, last updated 4 July 2026.

Read this before quoting: Outcomes reflect disputes that reached the First-tier Tribunal, not portfolio-wide quality. Small samples are noisy; every figure links to the underlying decisions.