In LON/00BD/LSC/2025/0853, decided 15 December 2025, the First-tier Tribunal considered 4 disputed service charge items at 36 Cherwell Court, Broom Park, TW11 9RT and found largely for the leaseholder: 4 items were reduced or disallowed. Full decision on GOV.UK below.

Property: 36 Cherwell Court, Broom Park, TW11 9RT
Decision date: 15 December 2025
Full decision: Read on GOV.UK

What was challenged and what the tribunal decided

ItemDemandedAllowedOutcomeGrounds
Gardening & grounds (2019-2023)£971.60£0Disallowed entirelyDemand formally invalid, Not payable under the lease
Legal & professional costs (2019-2023)£4,256.89—ReducedNot payable under the lease, Other grounds
Administration charges (2019-2023)£360£0Disallowed entirelyNot payable under the lease
Other charges (2019-2023)—£0Disallowed entirelyNot payable under the lease

Key passages (verbatim)

“The burden of proof is on the Applicant to show that the amounts claimed are payable and they have not done so.”
On gardening & grounds
“the wording of Clause 2(b) Part II of the Fifth Schedule is a clear contractual right to claim costs incurred in collecting the charge and legal costs are therefore payable in principle.”
On legal & professional costs
“Counsel for the Applicant accepted that the lease does not provide for the levying of a late payment fee.”
On administration charges
“Counsel for the Applicant also accepted that there was no contractual right to interest in the lease.”
On other charges
“During the hearing, the Tribunal were informed that the hearing had not been put in any diary by the Respondent's solicitors but they wished to attend but that all the solicitors were in a meeting.”
Of Respondent's solicitors

This summary is assembled from the structured record of the published decision; amounts appear only where the tribunal stated them. Always rely on the full decision itself.